Construction Controls on Baltic Eagle OSS
In addition to the new OSS construction "Arcadis Ost 1", b.offshore also supports the construction supervision of the second new OSS construction "Baltic Eagle" on behalf of 50Hertz.
The substation is being built by ENGIE Fabricom and Smulders in Antwerp / Belgium on behalf of the Spanish energy company Iberdrola. Like the other project, b.offshore will be continuously represented on site with up to five engineers until the completion of the OSS.
Further information can be found under the following links:
https://www.50hertz.com/de/Netz/Netzausbau/ProjekteaufSee/Ostwind2
https://www.iberdrola.com/about-us/lines-business/flagship-projects/baltic-eagle-offshore-wind-farm
https://www.engie-fabricom.com/